Client Update: “Lien”-ing Towards Efficiency: Upcoming Amendments to the Builders’ Lien Act

By Brian Tabor, QC and Colin Piercey

Bill 81 and Bill 15, receiving Royal Assent in 2013 and 2014 respectively, are due to take effect this month. On June 30, 2017, amendments to the Builders’ Lien Act (“the Act”) will introduce new regulations following recommendations from the 2013 Builders’ Lien Act Report by the Nova Scotia Law Reform Commission.

Why the Change?

The goal of these amendments is two-fold: to improve the flow of payments between certain stages of a construction project and to ensure that notice of important milestones, as defined by the Act, is given to parties involved.

To achieve these goals, the following amendments will take effect:

  • A progressive release of holdbacks to subcontractors through certification
  • A change in “finishing holdbacks”
  • The creation of a written notice requirement of substantial performance and subcontract completion

These amendments respond to a number of concerns related to the management of construction projects, specifically related to holdbacks and notice of contract performance timelines. As stated in a backgrounder on the upcoming amendments to the Act, the holdback system currently operates through a “construction pyramid,” whereby the owner retains a holdback from the contractor, and in turn, the contractor retains a holdback from the subcontractor. For example, if a contractor fails to pay their subcontractors, these individuals have the ability to place a “lien” on the owner’s property for the amount owed. If the construction project finishes and no liens are registered, the holdback is released. In other words, a holdback is used to protect owners by limiting liability and subcontractors in the event that the contractor defaults on the contract. These protections will not change.

Progressive Release of Holdbacks through Certification

Under the current Builders’ Lien Act, ­­the holdback retained by the owner may only be partially released (absent any liens being held) upon substantial completion of the contract and fully released upon final completion of the contract.  However, earlier subcontractors are often disadvantaged by the delay in receiving the holdback payment, with no interest payable on the holdback amount in the interim.

The amendments due to take effect will allow owners to release a subcontractor’s holdback earlier by having the completion of the subcontract certified under Subsection 13A of the Act by an architect or an engineer, or in their absence, by a court. In other words, owners and purchasers of a particular construction project will be able to rely on verification from an independent and qualified third party to release the holdback as opposed to waiting until substantial completion of the entire project occurs. The earlier subcontractor can be paid sooner while the owner still retains the protection afforded by the Act.

Once the subcontract is certified as complete, the owner must pay out a proportion of the holdback amount within 60 days. If the subcontractor’s holdback is not paid out within 65 days of certified completion, the owner will be liable to the subcontractor for interest on the holdback amount at a rate of prime plus 2 percent.

A Change in Finishing Holdbacks

Another change to the Act is the way that finishing holdbacks will be calculated moving forward. The current Act requires the owner to retain a holdback of 2.5 per cent of the entire contract price to cover any potential liens against the property registered after the substantial performance deadline. In practice, this amount is often disproportionate to the actual cost of the work remaining.

The amendments will change the calculation percentage of the finishing holdback to 10 per cent of the cost of the remaining work (such as the cost of remaining supplies and materials) rather than using 2.5 per cent of the entire contract price.

Written Notice Requirement of Substantial Performance or Completion

The amendments will also introduce a new set of regulations, NS Reg 72/2017 to improve the notice to be given to parties involved in the contract upon substantial performance or upon final completion. In practice, parties involved in a construction contract may not be informed of these particular milestones. Notice is important as it often acts as a trigger for the release of holdbacks if no lien against the property is filed.

The new regulations will impose a duty upon owners to make written notice available to parties working on a particular construction project, whether it be contractors, subcontractors, suppliers, or employees. The application of the regulations will not apply to an owner, their spouse, or common law partner for constructing a structure or for improving a building or land for single-family residential purposes, up to $75,000.

When and how does an owner give notice?

  • Post notice of substantial completion or subcontract completion of the construction project (depending on the milestone) within 10 days of the milestone date
  • Post notice on the publicly available portion of the Construction Association of Nova Scotia (CANS) website at www.substantialperformance.com (no fee for publishing, viewing, or searching for notices)
  • If there is a job site office, post notice in a prominent location

What does an owner include for notice of substantial completion?

  • Name and address of the owner
  • Name and address of the contractor
  • Description of the work or services performed
  • Description of the land upon which the work or services were performed
  • Date the contract was substantially performed

What does an owner include for notice of subcontract completion?

  • Name and address of the owner
  • Name and address of the contractor
  • Name and address of the subcontractor
  • If a subcontract is certified as complete under Subsection 13A of the Act, the name and address of the architect, engineer, or other person to whom the certificate payments are to be made
  • Description of the work or services performed or the materials placed or furnished
  • Description of the land upon which the work or services were performed or the materials were placed or furnished
  • Date the contract was certified as complete

The foregoing is intended for general information only. If you have any questions about how these amendments may affect your business, please contact a member of our Construction Law practice group.

References:

SHARE

Archive

Search Archive


 
 

Plans of arrangement come to Newfoundland and Labrador

January 30, 2024

By Tauna Staniland, K.C., ICD.D, Joe Thorne, and Nadine Otten What can you do when your corporation wants to complete a complex transaction requiring significant corporate restructuring that cannot be easily completed under the corporation’s…

Read More

Energy Watch

January 29, 2024

Stewart McKelvey is pleased to present Energy Watch – a review of key legislative and policy advancements in the renewable energy sector in 2023 in each of Newfoundland and Labrador, Nova Scotia and New Brunswick…

Read More

Beyond the border: A year end immigration wrap-up

December 21, 2023

We are pleased to present Beyond the border: A year end immigration wrap-up. Compiled by Lawyers from our Immigration team, this 2023 update covers topics including the Government of Canada’s ambitious immigration plans for the future;…

Read More

Land use planning in Prince Edward Island – the year in review

December 21, 2023

By Perlene Morrison, K.C., Hilary Newman & Curtis Doyle Once again, the time has come to review the year that was and to chart the course for the year ahead. For municipalities and planning professionals…

Read More

The Offshore Renewable Energy Area: Navigating offshore commitments in Newfoundland and Labrador

December 18, 2023

By Dave Randell, John Samms & Jayna Green A recent Government of Newfoundland and Labrador (“GNL”) announcement affirms the Province’s swift and ambitious approach to offshore wind development. While it may come as a shock…

Read More

Clean sweep: Federal Government tables legislation for Clean Technology Investment Tax Credit

December 15, 2023

By Sadira Jan, Dave Randell, Graham Haynes & Tyler Callahan On November 30, 2023, the Federal Government tabled Bill C-59, entitled An Act to implement certain provisions of the fall economic statement tabled in Parliament…

Read More

Forward focus: Canada’s ambitious immigration plan

December 14, 2023

By Brendan Sheridan The Government of Canada has continued their whirlwind year of immigration program announcements by revealing their plan to modernize and improve the country’s immigration system. This plan, known as “An Immigration System…

Read More

Preparing for Canada’s “Modern Slavery Act”: considerations and guidance for businesses

November 30, 2023

By Christine Pound, ICD.D, Rebecca Saturley, & Daniel Roth Canada’s anti-modern slavery legislation comes into force on January 1, 2024. To prepare for the first reporting deadline on May 31, 2024, organizations need to determine…

Read More

Replace-me-not: Bill C-58 proposes ban on replacement workers in federal strikes and lockouts

November 29, 2023

By Brian Johnston, K.C. and Richard Jordan On November 9, 2023, Minister of Labour, Seamus O’Regan, introduced Bill C-58 in the House of Commons to amend the Canada Labour Code to prohibit the use of…

Read More

Final retail payment activities regulations released

November 28, 2023

By Kevin Landry & Eryka Gregory The Retail Payment Activities Regulations (“Regulations”) under the Retail Payment Activities Act (“RPAA”) were finalized and published in the Canada Gazette Part II on November 23, 2023. The RPAA was…

Read More

Search Archive


Scroll To Top