Client Update: “Lien”-ing Towards Efficiency: Upcoming Amendments to the Builders’ Lien Act

By Brian Tabor, QC and Colin Piercey

Bill 81 and Bill 15, receiving Royal Assent in 2013 and 2014 respectively, are due to take effect this month. On June 30, 2017, amendments to the Builders’ Lien Act (“the Act”) will introduce new regulations following recommendations from the 2013 Builders’ Lien Act Report by the Nova Scotia Law Reform Commission.

Why the Change?

The goal of these amendments is two-fold: to improve the flow of payments between certain stages of a construction project and to ensure that notice of important milestones, as defined by the Act, is given to parties involved.

To achieve these goals, the following amendments will take effect:

  • A progressive release of holdbacks to subcontractors through certification
  • A change in “finishing holdbacks”
  • The creation of a written notice requirement of substantial performance and subcontract completion

These amendments respond to a number of concerns related to the management of construction projects, specifically related to holdbacks and notice of contract performance timelines. As stated in a backgrounder on the upcoming amendments to the Act, the holdback system currently operates through a “construction pyramid,” whereby the owner retains a holdback from the contractor, and in turn, the contractor retains a holdback from the subcontractor. For example, if a contractor fails to pay their subcontractors, these individuals have the ability to place a “lien” on the owner’s property for the amount owed. If the construction project finishes and no liens are registered, the holdback is released. In other words, a holdback is used to protect owners by limiting liability and subcontractors in the event that the contractor defaults on the contract. These protections will not change.

Progressive Release of Holdbacks through Certification

Under the current Builders’ Lien Act, ­­the holdback retained by the owner may only be partially released (absent any liens being held) upon substantial completion of the contract and fully released upon final completion of the contract.  However, earlier subcontractors are often disadvantaged by the delay in receiving the holdback payment, with no interest payable on the holdback amount in the interim.

The amendments due to take effect will allow owners to release a subcontractor’s holdback earlier by having the completion of the subcontract certified under Subsection 13A of the Act by an architect or an engineer, or in their absence, by a court. In other words, owners and purchasers of a particular construction project will be able to rely on verification from an independent and qualified third party to release the holdback as opposed to waiting until substantial completion of the entire project occurs. The earlier subcontractor can be paid sooner while the owner still retains the protection afforded by the Act.

Once the subcontract is certified as complete, the owner must pay out a proportion of the holdback amount within 60 days. If the subcontractor’s holdback is not paid out within 65 days of certified completion, the owner will be liable to the subcontractor for interest on the holdback amount at a rate of prime plus 2 percent.

A Change in Finishing Holdbacks

Another change to the Act is the way that finishing holdbacks will be calculated moving forward. The current Act requires the owner to retain a holdback of 2.5 per cent of the entire contract price to cover any potential liens against the property registered after the substantial performance deadline. In practice, this amount is often disproportionate to the actual cost of the work remaining.

The amendments will change the calculation percentage of the finishing holdback to 10 per cent of the cost of the remaining work (such as the cost of remaining supplies and materials) rather than using 2.5 per cent of the entire contract price.

Written Notice Requirement of Substantial Performance or Completion

The amendments will also introduce a new set of regulations, NS Reg 72/2017 to improve the notice to be given to parties involved in the contract upon substantial performance or upon final completion. In practice, parties involved in a construction contract may not be informed of these particular milestones. Notice is important as it often acts as a trigger for the release of holdbacks if no lien against the property is filed.

The new regulations will impose a duty upon owners to make written notice available to parties working on a particular construction project, whether it be contractors, subcontractors, suppliers, or employees. The application of the regulations will not apply to an owner, their spouse, or common law partner for constructing a structure or for improving a building or land for single-family residential purposes, up to $75,000.

When and how does an owner give notice?

  • Post notice of substantial completion or subcontract completion of the construction project (depending on the milestone) within 10 days of the milestone date
  • Post notice on the publicly available portion of the Construction Association of Nova Scotia (CANS) website at www.substantialperformance.com (no fee for publishing, viewing, or searching for notices)
  • If there is a job site office, post notice in a prominent location

What does an owner include for notice of substantial completion?

  • Name and address of the owner
  • Name and address of the contractor
  • Description of the work or services performed
  • Description of the land upon which the work or services were performed
  • Date the contract was substantially performed

What does an owner include for notice of subcontract completion?

  • Name and address of the owner
  • Name and address of the contractor
  • Name and address of the subcontractor
  • If a subcontract is certified as complete under Subsection 13A of the Act, the name and address of the architect, engineer, or other person to whom the certificate payments are to be made
  • Description of the work or services performed or the materials placed or furnished
  • Description of the land upon which the work or services were performed or the materials were placed or furnished
  • Date the contract was certified as complete

The foregoing is intended for general information only. If you have any questions about how these amendments may affect your business, please contact a member of our Construction Law practice group.

References:

SHARE

Archive

Search Archive


 
 

Nova Scotia offers new pension option to private sector employers

November 24, 2023

By Level Chan When proclaimed in force, the Nova Scotia Private Sector Pension Plan Transfer Act (the “Transfer Act”) enacted by Bill 339, Financial Measures (Fall 2023) Act will allow the transfer of private sector…

Read More

Bill C-365 calls for plan for implementation of open banking in Canada

November 17, 2023

By Kevin Landry On November 9 2023, Bill C-365, An Act respecting the implementation of a consumer-led banking system for Canadians (“C-365”), short titled as the ‘Consumer-led Banking Act’ was read in the House of…

Read More

More limits: NSCA tightens the test for disallowing a limitations defence

November 15, 2023

By Jennifer Taylor The Nova Scotia Court of Appeal (“NSCA”) has issued an important decision clarifying the test to disallow a limitations defence. The decision, Halifax (Regional Municipality) v Carvery (“Carvery”), has real implications for personal…

Read More

Anticipating changes to the Competition Act: what businesses need to know

November 1, 2023

By Deanne MacLeod, K.C., Burtley Francis & David Slipp On September 21, 2023, the Federal Government introduced Bill C-56: An Act to amend the Excise Tax Act and the Competition Act (“Bill C-56”), with the…

Read More

Powering the future: Green choice program regulations

September 22, 2023

By Nancy Rubin, K.C. and Lauren Agnew The long-awaited Green Choice Program Regulations (N.S. Reg. 155/2023) were released by the provincial government on September 8, 2023, offering some clarity into the practical implementation of Nova…

Read More

Privilege protected: Court of Appeal rules NL’s Information and Privacy Commissioner barred from reviewing solicitor-client privileged information

September 20, 2023

By Koren Thomson, John Samms, and Matthew Raske The Newfoundland and Labrador Court of Appeal has held that the Information and Privacy Commissioner for this province (the “Commissioner”) does not have the authority to order…

Read More

Amendments required for Prince Edward Island code of conduct bylaws

September 18, 2023

By Perlene Morrison, K.C. Municipalities are required to pass code of conduct bylaws in accordance with section 107 of the Municipal Government Act (the “MGA”). Subsection 107(1) of the MGA specifically states that a municipality’s…

Read More

Professionally speaking: Ontario Superior Court upholds professional regulators’ right to moderate speech

September 14, 2023

By Sheila Mecking and Kathleen Starke On August 23, 2023, the Ontario Superior Court (“ONSC”) upheld a complaints decision which ordered a psychologist to complete a continuing education or remedial program regarding professionalism in public…

Read More

One-year reminder for federal employers: Pay equity plans due September 3, 2024

September 5, 2023

By Dante Manna As we advised in a previous podcast, all federal employers with at least ten employees[1] have been subject to the Pay Equity Act [2] (“PEA”) and Pay Equity Regulations [3] (“Regulations”) since…

Read More

Charging to net-zero: Government releases draft Clean Electricity Regulations

August 23, 2023

By Nancy Rubin, K.C. Environment and Climate Change Canada (ECCC) recently published a draft of the Clean Electricity Regulations (CER). The proposed Regulations work toward achieving a net-zero electricity-generating sector, helping Canada become a net-zero…

Read More

Search Archive


Scroll To Top