Client Update: “Lien”-ing Towards Efficiency: Upcoming Amendments to the Builders’ Lien Act

By Brian Tabor, QC and Colin Piercey

Bill 81 and Bill 15, receiving Royal Assent in 2013 and 2014 respectively, are due to take effect this month. On June 30, 2017, amendments to the Builders’ Lien Act (“the Act”) will introduce new regulations following recommendations from the 2013 Builders’ Lien Act Report by the Nova Scotia Law Reform Commission.

Why the Change?

The goal of these amendments is two-fold: to improve the flow of payments between certain stages of a construction project and to ensure that notice of important milestones, as defined by the Act, is given to parties involved.

To achieve these goals, the following amendments will take effect:

  • A progressive release of holdbacks to subcontractors through certification
  • A change in “finishing holdbacks”
  • The creation of a written notice requirement of substantial performance and subcontract completion

These amendments respond to a number of concerns related to the management of construction projects, specifically related to holdbacks and notice of contract performance timelines. As stated in a backgrounder on the upcoming amendments to the Act, the holdback system currently operates through a “construction pyramid,” whereby the owner retains a holdback from the contractor, and in turn, the contractor retains a holdback from the subcontractor. For example, if a contractor fails to pay their subcontractors, these individuals have the ability to place a “lien” on the owner’s property for the amount owed. If the construction project finishes and no liens are registered, the holdback is released. In other words, a holdback is used to protect owners by limiting liability and subcontractors in the event that the contractor defaults on the contract. These protections will not change.

Progressive Release of Holdbacks through Certification

Under the current Builders’ Lien Act, ­­the holdback retained by the owner may only be partially released (absent any liens being held) upon substantial completion of the contract and fully released upon final completion of the contract.  However, earlier subcontractors are often disadvantaged by the delay in receiving the holdback payment, with no interest payable on the holdback amount in the interim.

The amendments due to take effect will allow owners to release a subcontractor’s holdback earlier by having the completion of the subcontract certified under Subsection 13A of the Act by an architect or an engineer, or in their absence, by a court. In other words, owners and purchasers of a particular construction project will be able to rely on verification from an independent and qualified third party to release the holdback as opposed to waiting until substantial completion of the entire project occurs. The earlier subcontractor can be paid sooner while the owner still retains the protection afforded by the Act.

Once the subcontract is certified as complete, the owner must pay out a proportion of the holdback amount within 60 days. If the subcontractor’s holdback is not paid out within 65 days of certified completion, the owner will be liable to the subcontractor for interest on the holdback amount at a rate of prime plus 2 percent.

A Change in Finishing Holdbacks

Another change to the Act is the way that finishing holdbacks will be calculated moving forward. The current Act requires the owner to retain a holdback of 2.5 per cent of the entire contract price to cover any potential liens against the property registered after the substantial performance deadline. In practice, this amount is often disproportionate to the actual cost of the work remaining.

The amendments will change the calculation percentage of the finishing holdback to 10 per cent of the cost of the remaining work (such as the cost of remaining supplies and materials) rather than using 2.5 per cent of the entire contract price.

Written Notice Requirement of Substantial Performance or Completion

The amendments will also introduce a new set of regulations, NS Reg 72/2017 to improve the notice to be given to parties involved in the contract upon substantial performance or upon final completion. In practice, parties involved in a construction contract may not be informed of these particular milestones. Notice is important as it often acts as a trigger for the release of holdbacks if no lien against the property is filed.

The new regulations will impose a duty upon owners to make written notice available to parties working on a particular construction project, whether it be contractors, subcontractors, suppliers, or employees. The application of the regulations will not apply to an owner, their spouse, or common law partner for constructing a structure or for improving a building or land for single-family residential purposes, up to $75,000.

When and how does an owner give notice?

  • Post notice of substantial completion or subcontract completion of the construction project (depending on the milestone) within 10 days of the milestone date
  • Post notice on the publicly available portion of the Construction Association of Nova Scotia (CANS) website at www.substantialperformance.com (no fee for publishing, viewing, or searching for notices)
  • If there is a job site office, post notice in a prominent location

What does an owner include for notice of substantial completion?

  • Name and address of the owner
  • Name and address of the contractor
  • Description of the work or services performed
  • Description of the land upon which the work or services were performed
  • Date the contract was substantially performed

What does an owner include for notice of subcontract completion?

  • Name and address of the owner
  • Name and address of the contractor
  • Name and address of the subcontractor
  • If a subcontract is certified as complete under Subsection 13A of the Act, the name and address of the architect, engineer, or other person to whom the certificate payments are to be made
  • Description of the work or services performed or the materials placed or furnished
  • Description of the land upon which the work or services were performed or the materials were placed or furnished
  • Date the contract was certified as complete

The foregoing is intended for general information only. If you have any questions about how these amendments may affect your business, please contact a member of our Construction Law practice group.

References:

SHARE

Archive

Search Archive


 
 

Client Update: New Nova Scotia Pension Benefits Act and Regulations effective June 1, 2015

April 23, 2015

On April 21, 2015, the Nova Scotia government declared that the new Pension Benefits Act (passed in 2011) and new Pension Benefits Regulations will come into effect on June 1, 2015. The new Regulations follow the new Act and draft Regulations summarized in…

Read More

Client Update: A Return to Reasonableness – Assessing Damages after Section D Settlements

April 4, 2015

An uninsured driver strikes another vehicle, injuring its occupants. These injured persons obtain a settlement from their own motor vehicle insurer (pursuant to Section D of the standard policy), and they assign their action against…

Read More

Atlantic Employers’ Counsel – Spring 2015

March 26, 2015

The Editors’ Corner Michelle Black and Sean Kelly Hello! We are very pleased to be the new Atlantic Employers’ Counsel (AEC) editors. We look forward to bringing you what we hope you will find to be interesting…

Read More

Client Update: The Employer’s implied contractual obligation to supply work: common law developments in employment law

March 10, 2015

Following several Supreme Court of Canada decisions in the late 1990s and early 2000s, the law of constructive dismissal was well defined – or so many thought. The Court’s decision in Potter v. New Brunswick Legal…

Read More

Client Update: Auto Insurance – Direct compensation for property damage is coming to PEI

March 5, 2015

In our May 20, 2014 client update, we reported on significant changes affecting automobile insurance in Prince Edward Island, including changes to no-fault benefits available under section B and changes to the damages cap for minor…

Read More

Labour and Employment Legislative Update 2014

February 10, 2015

2014 LABOUR AND EMPLOYMENT ATLANTIC CANADA LEGISLATIVE UPDATE As we move forward in 2015, we know our region’s employers will want to be aware of new legislation that has passed or could soon pass that…

Read More

Client Update: 2015 Minor Injury Cap

January 30, 2015

On January 28, 2015, the Office of the Superintendent of Insurance issued a bulletin in Nova Scotia. The 2015 minor injury cap has been set at $8,352, an increase of 1.7 per cent over 2014.…

Read More

Client Update: Outlook for the 2015 Proxy Season

January 29, 2015

In preparing for the 2015 proxy season, you should be aware of some regulatory changes that may impact disclosure to and interactions with your shareholders. This update highlights what is new in the 2015 proxy…

Read More

Client Update: Reaching New Limits – Recent Amendments to the PEI Lands Protection Act

January 6, 2015

During the Fall 2014 legislative sitting, the Province of Prince Edward Island passed legislation that results in significant changes to the Lands Protection Act. The amendments have just been proclaimed and were effective January 1, 2015.…

Read More

Atlantic Employers’ Counsel – Fall 2014

December 17, 2014

The Editor’s Corner Clarence Bennett This issue focuses on the family and the interaction between employment and family obligations. As 2014 comes to a close, I would like to extend Seasons Greetings to all of…

Read More

Search Archive


Scroll To Top