Once again, the time has come to review the year that was and to chart the course for the year ahead. For municipalities, developers and planning professionals throughout Prince Edward Island, this process often includes a survey of the decisions made by the Island Regulatory and Appeals Commission (“Commission”). The Commission is an independent tribunal that decides appeals from provincial and municipal land use planning decisions¹. In 2018, the Commission released one decision that engaged substantive planning principles. In this summary, we will review this decision and discuss its implications for municipalities, developers, and planning professionals in Prince Edward Island.

Discussion

In LA18-02, the Queens County Condominium Corporation (“Condo”) appealed a decision by the City of Charlottetown (“City”) to make a site-specific amendment to its zoning and development bylaw. The amendment followed an application by a developer to build a four-level, 23-unit apartment complex next to the Condo. In essence, the bylaw amendment approved changes that allowed the affordable housing project to proceed.

On appeal to the Commission, the Condo argued that the City made three errors:

 (i) the City breached its zoning and development bylaw by failing to obtain design review approval before issuing notice of the public meeting;

(ii) the City did not follow the advice of its planning staff; and

(iii) the apartment building was not the “best development” for the property.

The Commission rejected each of these arguments.

I. A technical breach of a bylaw does not always invalidate a municipal decision.

The City had two procedural obligations before it could approve the bylaw amendment:

(i) a design review was necessary because the property was located in a designated zone which required that an independent assessment of the development be completed to ensure its compatibility with the character of the surrounding area; and

(ii) a public meeting was required because the proposed development would exceed the maximum building height in the zone.

In this case, the City provided notice for the public meeting before the design review process had been completed. This was a potential problem because the bylaw stated that notice of the public meeting had to be issued after the review process was finished. The Condo therefore argued that the City had failed to follow the procedures set out in its bylaw.

The Commission concluded that, while the City made an error, it was not material to the outcome. The plans approved by the design reviewer were found by the Commission to be substantially similar to the plans presented by the developer at the public meeting. Also, the modifications suggested by the design reviewer – and accepted by the developer – did not relate to the complaints raised by the Condo at the public meeting. The Commission therefore found that the error was only technical in nature, and it did not prejudice the meeting process.

II. Conditions recommended by planning staff do not need to be expressly incorporated into the text of the amended bylaw.

Planning staff from the City had recommended approval of the amendment subject to certain conditions, which included obtaining final survey plans, design review approval, and a development agreement. However, the resolution from council approving the amendment did not reference these conditions expressly. The Condo argued that the City was obligated to include these conditions in the actual text of the bylaw amendment.

The Commission disagreed and found no error on the part of the City. The Commission noted that the resolution authorized the Mayor and the CEO to execute the contracts and agreements that were necessary to implement the resolution. The Commission found that this provision was sufficient to give effect to the recommendations made by the City’s planning staff. According to the Commission, the intention of council was to incorporate the conditions proposed by the planning staff into a subsequent development agreement between the City and the developer. The City therefore did not ignore the advice of its planning staff.

III. Determining whether a development satisfies sound planning principles generally requires expert evidence.

The Condo argued that the proposed apartment was not the “best possible development” for the property. In particular, the Condo cited health and safety concerns, including concerns about parking, the proximity of the development to the Condo, and the impact on density in the area. In support of its argument, the Condo called four witnesses at the hearing. However, none of its witnesses had any expertise in planning or development. Rather, the witnesses – all of whom were residents of the Condo – largely expressed their subjective concerns about the health and safety of the proposed development. In response, the City presented evidence from two professional planners.

The Commission did not accept the arguments advanced by the Condo for two main reasons:

  • First, the Commission held that the standard upon which to judge a development proposal was not “the best possible development” standard. Rather, the Commission found that, so long a development adheres to “sound planning principles,” its role is not to intervene with discretionary decisions made by a municipality. According to the Commission, holding developers to the standard of “best possible development” would frustrate building activity, maintain the status quo, and diminish the rights of landowners.
  • Second, in assessing whether the development satisfied sound planning principles, the Commission preferred the evidence of the City to that presented by the Condo. While the Commission acknowledged the health and safety concerns raised by the residents, it held that more robust evidence was required in order to find that sound planning principles were not satisfied. In particular, the Commission held that it required evidence that a development would violate an applicable law, or a recognized principle of land use planning, before it could overturn a planning decision of the City. By way of example, the Commission noted that this type of evidence may be provided by a police, fire, or security organization. Given that no such evidence was presented by the Condo, the Commission concluded that there was no basis upon which to find that the development did not satisfy sound planning principles.

Lessons for the New Year

Thousands of planning-related decisions are made each year in Prince Edward Island. Only a tiny fraction of those decisions are subject to review by the Commission. When that statistical reality is considered in light of the accessible right of appeal that is granted by the Planning Act², it signals that the provincial land use planning system is working and that the decisions made by our provincial and municipal decision-makers are generally accepted. The Commission, for its part, exercises an oversight function that searches for legal errors and procedural defects. Its decisions therefore serve as guideposts for municipalities, developers and planning professionals as they move forward – together – to use our most precious resource in ways that are principled, efficient, and sustainable.

Our hope is that this summary will also contribute to that objective in some small way. By drawing upon the lessons learned over the last year, decision-makers will not only minimize the risk of an appeal to the Commission, but also contribute to their proven record of making sound planning decisions for the benefit of Prince Edward Island and its residents.


¹ Outside the boundaries of incorporated municipalities, planning-related decisions are made by delegates of the Minister of Communities, Land and Environment.

² Generally speaking, any person who is dissatisfied with a planning-related decision can appeal to the Commission.  See Planning Act, R.S.P.E.I. 1988, c. P-8, ss. 28(1) and (1.1).

SHARE

Archive

Search Archive


 
 

Client Update: Universal interest arbitration proposed for New Brunswick

April 5, 2016

On March 29, 2016, the Province of New Brunswick tabled proposed changes to the Industrial Relations Act and the Public Services Labour Relations Act. If passed, these changes would dramatically alter well-established principles of private sector collective bargaining.…

Read More

Good Faith Fisheries: New case on Crown consultation & regulation of Aboriginal fisheries

March 22, 2016

By Jennifer Taylor Why is this case a big deal? It started with two salmon. Now, after several years of litigation, the Nova Scotia Provincial Court in R v Martin, 2016 NSPC 14 has stayed proceedings against…

Read More

Atlantic Employers’ Counsel – Winter 2016

March 10, 2016

THE EDITORS’ CORNER Michelle Black and Sean Kelly One day, the line between mental and physical disabilities may not be so pronounced, but, for now, distinctions are still drawn between Employee A with, for example, diabetes and…

Read More

Hiring the “Right” Employee

February 24, 2016

By Lisa Gallivan Employees can be your biggest asset, if you hire the right people. This can often be one of the biggest decisions that you make as a business owner or employer. The “right” employee…

Read More

Bye, Bye Canadian P.I.?: What Apple’s fight against the FBI means for the protection of Personal Information in Canada

February 23, 2016

By Burtley Francis and Kathleen Leighton Order Up: Apple, P.I. Recently, the public safety versus personal privacy debate has been brought to main headlines. Apple is facing a court order (available here) requiring the company to assist the FBI in the investigation of…

Read More

Client Update: Outlook for the 2016 Proxy Season

February 12, 2016

In preparing for the 2016 proxy season, you should be aware of some regulatory changes and institutional investor guidance that may impact disclosure to and interactions with your shareholders. This update highlights what is new…

Read More

Left Sharks and Copy Cats: The Super Bowl’s Impact on Protecting a Brand

February 5, 2016

By Burtley Francis and Michael MacIsaac You remember Left Shark… The Super Bowl is a lot of things to a lot of people and is arguably the most anticipated event of the year that is not a holiday…

Read More

The Labour Relations of First Nations’ Fisheries: Who gets to decide?

February 2, 2016

By Jennifer Taylor Summary The Canada Industrial Relations Board recently held that it had no jurisdiction as a federal board to certify a bargaining unit comprised of fisheries employees of the Waycobah First Nation. The decision…

Read More

Can an employer prohibit tattoos and piercings?

January 21, 2016

By Peter McLellan, QC In the 1970s the issue for employers was long hair and sideburns. In the 1980’s it was earrings for men. Today the employer’s concerns are with tattoos and facial piercings. What are…

Read More

Settling for it: Two new NS decisions on settlement agreements and releases

January 15, 2016

By Jennifer Taylor Introduction It sounds simple: Two disputing parties, hoping to resolve their disagreement without drawn-out court proceedings, will mutually agree to a settlement on clear terms; release each other from all claims; and move…

Read More

Search Archive


Scroll To Top