Skip to content

Client Update: Special Project Orders the next milestone for Muskrat Falls progress

On June 17, 2013, pursuant to the recently amended Section 70 of the Labour Relations Act for Newfoundland and Labrador (“NL”), the Government of Newfoundland and Labrador issued three Special Project Orders (“SPOs”) in respect of the Muskrat Falls phase of the Lower Churchill Hydro Electric Generation Project (“Muskrat Falls Project”).

For those seeking to do work on the Muskrat Falls Project, familiarization with the SPOs and the referenced agreements is essential.

The SPOs have the effect of displacing the collective agreements negotiated between the Construction Labour Relations Association (the accredited employer in the Commercial Industrial Division of the NL construction industry) and the individual trade unions who represent the tradespersons in that division. They also operate to create a virtually exclusive unionized workplace.

The SPOs and the prescribed Collective Agreements designate three separate work scopes for the Muskrat Falls Project, each with its own collective agreement and an umbrella dispute resolution agreement.

The three work scopes of the Muskrat Falls Project are:

  • Lower Churchill reservoir clearing
  • Lower Churchill hydro generation
  • Lower Churchill transmission

The umbrella agreement for dispute resolution, the Overlap Dispute Resolution Agreement, is designed to resolve disputes where there are overlaps in the work of one or more contractors on two or more of the three separate work scopes of the Muskrat Falls Project.

Care must be taken not to assume that the collective agreements for each work scope of the Muskrat Falls Project follow the pattern of previous SPOs or that all the construction trades are involved with a special project collective agreement respecting a particular scope of work; there are three distinct collective agreements in respect of the Muskrat Falls Project as a whole.

The Special Project collective agreements allow a union or non-union contractor to become involved on the site but, whether union or non-union, a contractor is obligated to acquire its labour in accordance with the applicable Special Project Agreement hiring protocols. The hiring protocols are consistent with the Lower Churchill Construction Projects Benefits Strategy and Lower Churchill Innu Impacts and Benefits Agreement. These agreements ensure priority of hiring for qualified Labrador Innu, qualified Labrador residents and qualified residents of the Island portion of the Province. Unionized contractors may have some flexibility respecting use of their regular unionized employees on the Muskrat Falls Project, but non-union contractors have little to no flexibility in this regard.

The three collective agreements which have been prescribed for the three separate work scopes of the Muskrat Falls Project are:

  • Collective Agreement between Muskrat Falls Employers’ Association and the Resource Development Trades Council of Newfoundland and Labrador* (Generating Facility Agreement).
    –  The Trades Council represents all construction trades operating
    in the Province.
  • Collective Agreement between Lower Churchill Transmission Construction Employers’ Association Inc. and International Brotherhood of Electrical Workers, Local 1620 (Transmission Agreement).
  • Collective Agreement between Lower Churchill Reservoir Clearing Employers’ Association Inc. and Labourers’ International Union of North America and the Construction and General Labourers’ Union, Rock and Tunnel Workers, Local 1208 (Reservoir Clearing Agreement).

It is recommended that clients review, paying particular attention to, the collective agreement related to the scope of the work targeted and, where there exists overlap, the collective agreement relevant to either or both of the work scopes prescribed by the other SPOs. It is also recommended that the Overlap Dispute Resolution Agreement be reviewed in order to fully understand the financial and labour cost implications of work which may involve two or more of the work scopes within the Muskrat Falls Project.

As with previous special projects, a non-union contractor which follows the hiring provisions of the applicable Special Project Agreement(s) does not automatically become a unionized contractor at the conclusion of work on the Special Project. In the Muskrat Falls Project wind-down process each contractor who is non-union prior to commencing work on the Special Project should ensure care is taken during its layoff and wind-down processes. Similarly, a contractor bound by one or more of the Provincial Commercial Industrial Division collective agreements when commencing work on the Special Project may avoid the applicability of additional Provincial agreements by exercising care during its layoff and wind-down process as the work is completed.

The issuance of the SPOs marks another significant milestone in the recently sanctioned $7.7 billion dollar Muskrat Falls Project.

We would be pleased to assist with any legal and strategic planning issues arising from proposed or actual involvement in the Muskrat Falls Project.

SHARE

Archive

Search Archive


 
 

Client Update: Reaching New Limits – Recent Amendments to the PEI Lands Protection Act

January 6, 2015

During the Fall 2014 legislative sitting, the Province of Prince Edward Island passed legislation that results in significant changes to the Lands Protection Act. The amendments have just been proclaimed and were effective January 1, 2015.…

Read More

Atlantic Employers’ Counsel – Fall 2014

December 17, 2014

The Editor’s Corner Clarence Bennett This issue focuses on the family and the interaction between employment and family obligations. As 2014 comes to a close, I would like to extend Seasons Greetings to all of…

Read More

Client Update: Recent Developments: Disability Insurance Policies

December 17, 2014

RECENT DEVELOPMENTS: DISABILITY INSURANCE POLICIES & LIMITATION PERIODS IN NOVA SCOTIA Two recent Nova Scotia decisions have clarified the issue of limitation periods in disability insurance policies and “rolling” limitation periods.   THORNTON V. RBC…

Read More

Client Update: Changes to Related Party Election (Section 156 – Excise Tax Act)

December 16, 2014

Section 156 of the Excise Tax Act (the “ETA“) provides an election that relieves certain related parties from having to collect Harmonized Sales Tax (“HST“) on the goods and services sold between them. The election deems qualifying…

Read More

Doing Business in Atlantic Canada (Fall 2014) (Canadian Lawyer Magazine Supplement)

November 20, 2014

IN THIS ISSUE: More Than Wind – Emergence of Tidal Energy in Atlantic Canada by Sadira Jan Aquaculture and Salmon Farming in Atlantic Canada by Greg Harding The Expanding Atlantic Canada Offshore Industry: Growing Offshore without Going Offside by Stephen Penney and Rebecca…

Read More

Client Update: Truth or Consequences – The New Duty of Honest Performance in Commercial Contracts

November 17, 2014

The Supreme Court of Canada’s unanimous decision in the breach of contract case Bhasin v Hrynew, 2014 SCC 71 was released on November 13, 2014. The case is important in the law of contracts because…

Read More

Client Update: Recent Changes to the Temporary Foreign Worker Program

August 28, 2014

On June 20, 2014, the Government of Canada announced a series of reforms to overhaul the Temporary Foreign Worker Program (“TFWP”). These reforms, many of which are effective immediately, function to: Re-organize the TFWP  The…

Read More

Atlantic Employers’ Counsel – Summer 2014

August 1, 2014

The Editor’s Corner Clarence Bennett Summer is halfway over, but we know you will want to take this edition along with you while you enjoy more summer weather and time out of the office. Employers…

Read More

Client Update – Tsilhqot’in Nation – An East Coast Perspective

July 9, 2014

On June 26, 2014, the Supreme Court of Canada released one of the most significant aboriginal law decisions since Marshall – Tsilhqot’in Nation v. British Columbia, 2014 SCC 44 (also known as the William decision).  This decision could have…

Read More

Client Update: Nova Scotia Supreme Court awards $500,000 in Punitive Damages in LTD case

July 9, 2014

In Industrial Alliance Insurance and Financial Services Inc. v. Brine, 2014 NSSC 219, National Life (and later its successor Industrial Alliance) alleged Brine had received undisclosed CPP and Superannuation disability benefits resulting in a substantial overpayment of…

Read More

Search Archive


Scroll To Top