Once again, the time has come to review the year that was and to chart the course for the year ahead. For municipalities, developers and planning professionals throughout Prince Edward Island, this process often includes a survey of the decisions made by the Island Regulatory and Appeals Commission (“Commission”). The Commission is an independent tribunal that decides appeals from provincial and municipal land use planning decisions¹. In 2018, the Commission released one decision that engaged substantive planning principles. In this summary, we will review this decision and discuss its implications for municipalities, developers, and planning professionals in Prince Edward Island.

Discussion

In LA18-02, the Queens County Condominium Corporation (“Condo”) appealed a decision by the City of Charlottetown (“City”) to make a site-specific amendment to its zoning and development bylaw. The amendment followed an application by a developer to build a four-level, 23-unit apartment complex next to the Condo. In essence, the bylaw amendment approved changes that allowed the affordable housing project to proceed.

On appeal to the Commission, the Condo argued that the City made three errors:

 (i) the City breached its zoning and development bylaw by failing to obtain design review approval before issuing notice of the public meeting;

(ii) the City did not follow the advice of its planning staff; and

(iii) the apartment building was not the “best development” for the property.

The Commission rejected each of these arguments.

I. A technical breach of a bylaw does not always invalidate a municipal decision.

The City had two procedural obligations before it could approve the bylaw amendment:

(i) a design review was necessary because the property was located in a designated zone which required that an independent assessment of the development be completed to ensure its compatibility with the character of the surrounding area; and

(ii) a public meeting was required because the proposed development would exceed the maximum building height in the zone.

In this case, the City provided notice for the public meeting before the design review process had been completed. This was a potential problem because the bylaw stated that notice of the public meeting had to be issued after the review process was finished. The Condo therefore argued that the City had failed to follow the procedures set out in its bylaw.

The Commission concluded that, while the City made an error, it was not material to the outcome. The plans approved by the design reviewer were found by the Commission to be substantially similar to the plans presented by the developer at the public meeting. Also, the modifications suggested by the design reviewer – and accepted by the developer – did not relate to the complaints raised by the Condo at the public meeting. The Commission therefore found that the error was only technical in nature, and it did not prejudice the meeting process.

II. Conditions recommended by planning staff do not need to be expressly incorporated into the text of the amended bylaw.

Planning staff from the City had recommended approval of the amendment subject to certain conditions, which included obtaining final survey plans, design review approval, and a development agreement. However, the resolution from council approving the amendment did not reference these conditions expressly. The Condo argued that the City was obligated to include these conditions in the actual text of the bylaw amendment.

The Commission disagreed and found no error on the part of the City. The Commission noted that the resolution authorized the Mayor and the CEO to execute the contracts and agreements that were necessary to implement the resolution. The Commission found that this provision was sufficient to give effect to the recommendations made by the City’s planning staff. According to the Commission, the intention of council was to incorporate the conditions proposed by the planning staff into a subsequent development agreement between the City and the developer. The City therefore did not ignore the advice of its planning staff.

III. Determining whether a development satisfies sound planning principles generally requires expert evidence.

The Condo argued that the proposed apartment was not the “best possible development” for the property. In particular, the Condo cited health and safety concerns, including concerns about parking, the proximity of the development to the Condo, and the impact on density in the area. In support of its argument, the Condo called four witnesses at the hearing. However, none of its witnesses had any expertise in planning or development. Rather, the witnesses – all of whom were residents of the Condo – largely expressed their subjective concerns about the health and safety of the proposed development. In response, the City presented evidence from two professional planners.

The Commission did not accept the arguments advanced by the Condo for two main reasons:

  • First, the Commission held that the standard upon which to judge a development proposal was not “the best possible development” standard. Rather, the Commission found that, so long a development adheres to “sound planning principles,” its role is not to intervene with discretionary decisions made by a municipality. According to the Commission, holding developers to the standard of “best possible development” would frustrate building activity, maintain the status quo, and diminish the rights of landowners.
  • Second, in assessing whether the development satisfied sound planning principles, the Commission preferred the evidence of the City to that presented by the Condo. While the Commission acknowledged the health and safety concerns raised by the residents, it held that more robust evidence was required in order to find that sound planning principles were not satisfied. In particular, the Commission held that it required evidence that a development would violate an applicable law, or a recognized principle of land use planning, before it could overturn a planning decision of the City. By way of example, the Commission noted that this type of evidence may be provided by a police, fire, or security organization. Given that no such evidence was presented by the Condo, the Commission concluded that there was no basis upon which to find that the development did not satisfy sound planning principles.

Lessons for the New Year

Thousands of planning-related decisions are made each year in Prince Edward Island. Only a tiny fraction of those decisions are subject to review by the Commission. When that statistical reality is considered in light of the accessible right of appeal that is granted by the Planning Act², it signals that the provincial land use planning system is working and that the decisions made by our provincial and municipal decision-makers are generally accepted. The Commission, for its part, exercises an oversight function that searches for legal errors and procedural defects. Its decisions therefore serve as guideposts for municipalities, developers and planning professionals as they move forward – together – to use our most precious resource in ways that are principled, efficient, and sustainable.

Our hope is that this summary will also contribute to that objective in some small way. By drawing upon the lessons learned over the last year, decision-makers will not only minimize the risk of an appeal to the Commission, but also contribute to their proven record of making sound planning decisions for the benefit of Prince Edward Island and its residents.


¹ Outside the boundaries of incorporated municipalities, planning-related decisions are made by delegates of the Minister of Communities, Land and Environment.

² Generally speaking, any person who is dissatisfied with a planning-related decision can appeal to the Commission.  See Planning Act, R.S.P.E.I. 1988, c. P-8, ss. 28(1) and (1.1).

SHARE

Archive

Search Archive


 
 

Client Update: Reaching New Limits – Recent Amendments to the PEI Lands Protection Act

January 6, 2015

During the Fall 2014 legislative sitting, the Province of Prince Edward Island passed legislation that results in significant changes to the Lands Protection Act. The amendments have just been proclaimed and were effective January 1, 2015.…

Read More

Atlantic Employers’ Counsel – Fall 2014

December 17, 2014

The Editor’s Corner Clarence Bennett This issue focuses on the family and the interaction between employment and family obligations. As 2014 comes to a close, I would like to extend Seasons Greetings to all of…

Read More

Client Update: Recent Developments: Disability Insurance Policies

December 17, 2014

RECENT DEVELOPMENTS: DISABILITY INSURANCE POLICIES & LIMITATION PERIODS IN NOVA SCOTIA Two recent Nova Scotia decisions have clarified the issue of limitation periods in disability insurance policies and “rolling” limitation periods.   THORNTON V. RBC…

Read More

Client Update: Changes to Related Party Election (Section 156 – Excise Tax Act)

December 16, 2014

Section 156 of the Excise Tax Act (the “ETA“) provides an election that relieves certain related parties from having to collect Harmonized Sales Tax (“HST“) on the goods and services sold between them. The election deems qualifying…

Read More

Doing Business in Atlantic Canada (Fall 2014) (Canadian Lawyer Magazine Supplement)

November 20, 2014

IN THIS ISSUE: More Than Wind – Emergence of Tidal Energy in Atlantic Canada by Sadira Jan Aquaculture and Salmon Farming in Atlantic Canada by Greg Harding The Expanding Atlantic Canada Offshore Industry: Growing Offshore without Going Offside by Stephen Penney and Rebecca…

Read More

Client Update: Truth or Consequences – The New Duty of Honest Performance in Commercial Contracts

November 17, 2014

The Supreme Court of Canada’s unanimous decision in the breach of contract case Bhasin v Hrynew, 2014 SCC 71 was released on November 13, 2014. The case is important in the law of contracts because…

Read More

Client Update: Recent Changes to the Temporary Foreign Worker Program

August 28, 2014

On June 20, 2014, the Government of Canada announced a series of reforms to overhaul the Temporary Foreign Worker Program (“TFWP”). These reforms, many of which are effective immediately, function to: Re-organize the TFWP  The…

Read More

Atlantic Employers’ Counsel – Summer 2014

August 1, 2014

The Editor’s Corner Clarence Bennett Summer is halfway over, but we know you will want to take this edition along with you while you enjoy more summer weather and time out of the office. Employers…

Read More

Client Update – Tsilhqot’in Nation – An East Coast Perspective

July 9, 2014

On June 26, 2014, the Supreme Court of Canada released one of the most significant aboriginal law decisions since Marshall – Tsilhqot’in Nation v. British Columbia, 2014 SCC 44 (also known as the William decision).  This decision could have…

Read More

Client Update: Nova Scotia Supreme Court awards $500,000 in Punitive Damages in LTD case

July 9, 2014

In Industrial Alliance Insurance and Financial Services Inc. v. Brine, 2014 NSSC 219, National Life (and later its successor Industrial Alliance) alleged Brine had received undisclosed CPP and Superannuation disability benefits resulting in a substantial overpayment of…

Read More

Search Archive


Scroll To Top