Client Update: “Lien”-ing Towards Efficiency: Upcoming Amendments to the Builders’ Lien Act

By Brian Tabor, QC and Colin Piercey

Bill 81 and Bill 15, receiving Royal Assent in 2013 and 2014 respectively, are due to take effect this month. On June 30, 2017, amendments to the Builders’ Lien Act (“the Act”) will introduce new regulations following recommendations from the 2013 Builders’ Lien Act Report by the Nova Scotia Law Reform Commission.

Why the Change?

The goal of these amendments is two-fold: to improve the flow of payments between certain stages of a construction project and to ensure that notice of important milestones, as defined by the Act, is given to parties involved.

To achieve these goals, the following amendments will take effect:

  • A progressive release of holdbacks to subcontractors through certification
  • A change in “finishing holdbacks”
  • The creation of a written notice requirement of substantial performance and subcontract completion

These amendments respond to a number of concerns related to the management of construction projects, specifically related to holdbacks and notice of contract performance timelines. As stated in a backgrounder on the upcoming amendments to the Act, the holdback system currently operates through a “construction pyramid,” whereby the owner retains a holdback from the contractor, and in turn, the contractor retains a holdback from the subcontractor. For example, if a contractor fails to pay their subcontractors, these individuals have the ability to place a “lien” on the owner’s property for the amount owed. If the construction project finishes and no liens are registered, the holdback is released. In other words, a holdback is used to protect owners by limiting liability and subcontractors in the event that the contractor defaults on the contract. These protections will not change.

Progressive Release of Holdbacks through Certification

Under the current Builders’ Lien Act, ­­the holdback retained by the owner may only be partially released (absent any liens being held) upon substantial completion of the contract and fully released upon final completion of the contract.  However, earlier subcontractors are often disadvantaged by the delay in receiving the holdback payment, with no interest payable on the holdback amount in the interim.

The amendments due to take effect will allow owners to release a subcontractor’s holdback earlier by having the completion of the subcontract certified under Subsection 13A of the Act by an architect or an engineer, or in their absence, by a court. In other words, owners and purchasers of a particular construction project will be able to rely on verification from an independent and qualified third party to release the holdback as opposed to waiting until substantial completion of the entire project occurs. The earlier subcontractor can be paid sooner while the owner still retains the protection afforded by the Act.

Once the subcontract is certified as complete, the owner must pay out a proportion of the holdback amount within 60 days. If the subcontractor’s holdback is not paid out within 65 days of certified completion, the owner will be liable to the subcontractor for interest on the holdback amount at a rate of prime plus 2 percent.

A Change in Finishing Holdbacks

Another change to the Act is the way that finishing holdbacks will be calculated moving forward. The current Act requires the owner to retain a holdback of 2.5 per cent of the entire contract price to cover any potential liens against the property registered after the substantial performance deadline. In practice, this amount is often disproportionate to the actual cost of the work remaining.

The amendments will change the calculation percentage of the finishing holdback to 10 per cent of the cost of the remaining work (such as the cost of remaining supplies and materials) rather than using 2.5 per cent of the entire contract price.

Written Notice Requirement of Substantial Performance or Completion

The amendments will also introduce a new set of regulations, NS Reg 72/2017 to improve the notice to be given to parties involved in the contract upon substantial performance or upon final completion. In practice, parties involved in a construction contract may not be informed of these particular milestones. Notice is important as it often acts as a trigger for the release of holdbacks if no lien against the property is filed.

The new regulations will impose a duty upon owners to make written notice available to parties working on a particular construction project, whether it be contractors, subcontractors, suppliers, or employees. The application of the regulations will not apply to an owner, their spouse, or common law partner for constructing a structure or for improving a building or land for single-family residential purposes, up to $75,000.

When and how does an owner give notice?

  • Post notice of substantial completion or subcontract completion of the construction project (depending on the milestone) within 10 days of the milestone date
  • Post notice on the publicly available portion of the Construction Association of Nova Scotia (CANS) website at www.substantialperformance.com (no fee for publishing, viewing, or searching for notices)
  • If there is a job site office, post notice in a prominent location

What does an owner include for notice of substantial completion?

  • Name and address of the owner
  • Name and address of the contractor
  • Description of the work or services performed
  • Description of the land upon which the work or services were performed
  • Date the contract was substantially performed

What does an owner include for notice of subcontract completion?

  • Name and address of the owner
  • Name and address of the contractor
  • Name and address of the subcontractor
  • If a subcontract is certified as complete under Subsection 13A of the Act, the name and address of the architect, engineer, or other person to whom the certificate payments are to be made
  • Description of the work or services performed or the materials placed or furnished
  • Description of the land upon which the work or services were performed or the materials were placed or furnished
  • Date the contract was certified as complete

The foregoing is intended for general information only. If you have any questions about how these amendments may affect your business, please contact a member of our Construction Law practice group.

References:

SHARE

Archive

Search Archive


 
 

The boomerang that won’t come back – Court of Appeal confirms that parties must each bring their own motions for summary judgment

September 25, 2020

Chad Sullivan and Kathleen Nash In a recent decision from the New Brunswick Court of Appeal, Abrams v RTO Asset Management, 2020 NBCA 57, the court clarified the procedure for seeking summary judgment and addresses…

Read More

The limits of open work permits

September 23, 2020

Kathleen Leighton In Canada, foreign nationals have various options to obtain either “employer-specific” or “open” work permits – we discuss this distinction in greater detail here. Open work permits can be obtained by individuals in…

Read More

Supreme Court of Canada may re-consider municipal liability for policy vs. operational decisions

September 23, 2020

Giles Ayers and Joe Thorne Introduction Balancing a municipal budget has always been a challenging task in Newfoundland and Labrador, and this is particularly true in a year of extreme weather events and a global…

Read More

Beyond the border: Immigration update – September 2020

September 8, 2020

We are pleased to present the third installment of Beyond the border, a publication aimed at providing the latest information to clients about new programs and other immigration-related information that may be pertinent to employers of…

Read More

Newfoundland and Labrador mandates masks in workplaces

August 24, 2020

Harold M. Smith, QC and G. John Samms Effective Monday, August 24, 2020, an order directing the mandatory wearing of masks, pursuant to the Public Health and Protection Act and the Special Measures Orders made…

Read More

New Brunswick’s new Enduring Powers of Attorney Act

August 10, 2020

Gerald McMackin, QC and Christopher Marr, TEP New Brunswick joined the rest of Canada in enacting legislation that deals solely with powers of attorney when the Enduring Powers of Attorney Act (“Act”) came into force…

Read More

Prince Edward Island Labour and Employment legislative changes

July 31, 2020

Murray Murphy, QC, CPHR and Kate Jurgens Three new bills have been introduced in the most recent sitting of the Prince Edward Island legislature. In the employment setting Bill 38 aims to address the prevalence…

Read More

Game over for waiver of tort

July 27, 2020

Jennifer Taylor   The Supreme Court of Canada has finally put an end to the “waiver of tort” debate.   After years of uncertainty, a majority of the Court confirmed in Atlantic Lottery Corp Inc…

Read More

COVID-19 – potential liability for municipalities

July 21, 2020

Stephen Penney and Justin Hewitt As municipalities begin opening up recreational facilities in Alert Level 2 of the COVID-19 public health emergency implemented by the Provincial Government, Municipalities Newfoundland and Labrador has been receiving inquiries…

Read More

Applicability of business tax where operations limited

July 21, 2020

There is no obligation upon a municipality to reduce a business tax due to limited operations secondary to the COVID-19 pandemic. A municipality does, however, have the discretion to offer business tax relief. If a…

Read More

Search Archive


Scroll To Top