Client Update: “Lien”-ing Towards Efficiency: Upcoming Amendments to the Builders’ Lien Act

By Brian Tabor, QC and Colin Piercey

Bill 81 and Bill 15, receiving Royal Assent in 2013 and 2014 respectively, are due to take effect this month. On June 30, 2017, amendments to the Builders’ Lien Act (“the Act”) will introduce new regulations following recommendations from the 2013 Builders’ Lien Act Report by the Nova Scotia Law Reform Commission.

Why the Change?

The goal of these amendments is two-fold: to improve the flow of payments between certain stages of a construction project and to ensure that notice of important milestones, as defined by the Act, is given to parties involved.

To achieve these goals, the following amendments will take effect:

  • A progressive release of holdbacks to subcontractors through certification
  • A change in “finishing holdbacks”
  • The creation of a written notice requirement of substantial performance and subcontract completion

These amendments respond to a number of concerns related to the management of construction projects, specifically related to holdbacks and notice of contract performance timelines. As stated in a backgrounder on the upcoming amendments to the Act, the holdback system currently operates through a “construction pyramid,” whereby the owner retains a holdback from the contractor, and in turn, the contractor retains a holdback from the subcontractor. For example, if a contractor fails to pay their subcontractors, these individuals have the ability to place a “lien” on the owner’s property for the amount owed. If the construction project finishes and no liens are registered, the holdback is released. In other words, a holdback is used to protect owners by limiting liability and subcontractors in the event that the contractor defaults on the contract. These protections will not change.

Progressive Release of Holdbacks through Certification

Under the current Builders’ Lien Act, ­­the holdback retained by the owner may only be partially released (absent any liens being held) upon substantial completion of the contract and fully released upon final completion of the contract.  However, earlier subcontractors are often disadvantaged by the delay in receiving the holdback payment, with no interest payable on the holdback amount in the interim.

The amendments due to take effect will allow owners to release a subcontractor’s holdback earlier by having the completion of the subcontract certified under Subsection 13A of the Act by an architect or an engineer, or in their absence, by a court. In other words, owners and purchasers of a particular construction project will be able to rely on verification from an independent and qualified third party to release the holdback as opposed to waiting until substantial completion of the entire project occurs. The earlier subcontractor can be paid sooner while the owner still retains the protection afforded by the Act.

Once the subcontract is certified as complete, the owner must pay out a proportion of the holdback amount within 60 days. If the subcontractor’s holdback is not paid out within 65 days of certified completion, the owner will be liable to the subcontractor for interest on the holdback amount at a rate of prime plus 2 percent.

A Change in Finishing Holdbacks

Another change to the Act is the way that finishing holdbacks will be calculated moving forward. The current Act requires the owner to retain a holdback of 2.5 per cent of the entire contract price to cover any potential liens against the property registered after the substantial performance deadline. In practice, this amount is often disproportionate to the actual cost of the work remaining.

The amendments will change the calculation percentage of the finishing holdback to 10 per cent of the cost of the remaining work (such as the cost of remaining supplies and materials) rather than using 2.5 per cent of the entire contract price.

Written Notice Requirement of Substantial Performance or Completion

The amendments will also introduce a new set of regulations, NS Reg 72/2017 to improve the notice to be given to parties involved in the contract upon substantial performance or upon final completion. In practice, parties involved in a construction contract may not be informed of these particular milestones. Notice is important as it often acts as a trigger for the release of holdbacks if no lien against the property is filed.

The new regulations will impose a duty upon owners to make written notice available to parties working on a particular construction project, whether it be contractors, subcontractors, suppliers, or employees. The application of the regulations will not apply to an owner, their spouse, or common law partner for constructing a structure or for improving a building or land for single-family residential purposes, up to $75,000.

When and how does an owner give notice?

  • Post notice of substantial completion or subcontract completion of the construction project (depending on the milestone) within 10 days of the milestone date
  • Post notice on the publicly available portion of the Construction Association of Nova Scotia (CANS) website at www.substantialperformance.com (no fee for publishing, viewing, or searching for notices)
  • If there is a job site office, post notice in a prominent location

What does an owner include for notice of substantial completion?

  • Name and address of the owner
  • Name and address of the contractor
  • Description of the work or services performed
  • Description of the land upon which the work or services were performed
  • Date the contract was substantially performed

What does an owner include for notice of subcontract completion?

  • Name and address of the owner
  • Name and address of the contractor
  • Name and address of the subcontractor
  • If a subcontract is certified as complete under Subsection 13A of the Act, the name and address of the architect, engineer, or other person to whom the certificate payments are to be made
  • Description of the work or services performed or the materials placed or furnished
  • Description of the land upon which the work or services were performed or the materials were placed or furnished
  • Date the contract was certified as complete

The foregoing is intended for general information only. If you have any questions about how these amendments may affect your business, please contact a member of our Construction Law practice group.

References:

SHARE

Archive

Search Archive


 
 

Halifax lawyers create a resource for STEP Canada outlining temporary estate document signing protocols by province during the COVID19 Pandemic

April 27, 2020

Halifax Partners Richard Niedermayer, TEP, Secretary, STEP Canada, and Tim Matthews, QC, TEP, and Articled Clerk Madeleine Coats, have prepared a useful resource for STEP Canada members outlining the options in place for having estate…

Read More

Update on Newfoundland and Labrador variation of limitation periods and statutory timelines during COVID-19 pandemic

April 27, 2020

Joe Thorne In our update on April 2, 2020, Newfoundland and Labrador passes law to allow variation periods and statutory timelines during COVID-19 pandemic, we reported on Newfoundland and Labrador’s passage of the Temporary Variation…

Read More

Think: roadmap to recovery – Saskatchewan’s re-open plan is worthy of consideration

April 24, 2020

Rick Dunlop The question on many businesses’ mind is when and what exactly does an end to the COVID-19 lockdown look like. The Economist describes various European government’s easing of COVID-19 restrictions as being done…

Read More

Enhanced scrutiny of foreign investments during COVID-19

April 24, 2020

Burtley Francis In a statement issued on April 18, 20201, the federal government (through Innovation, Science and Economic Development Canada) signalled that certain foreign investments into Canada will now face enhanced scrutiny under the Investment…

Read More

An update on the impacts of COVID-19 on the tax dispute resolution process

April 21, 2020

Stephanie Stapleford and Allison Whelan,LL.M In a previous Thought Leadership piece, “Tax update – response to COVID-19” (26 March 2020), we reviewed the Federal COVID-19 Emergency Response Act and provided an update on operational changes…

Read More

Did the Government of New Brunswick pave the way for employees to refuse to work during the State of Emergency?

April 20, 2020

Clarence Bennett, James LeMesurier, QC and Kathleen Nash On April 17, 2020, the Legislative Assembly of New Brunswick met for a quick sitting during which two new Bills were introduced and received Royal Assent within…

Read More

Competition compliance risks during the COVID-19 crisis: Increased scrutiny of price-gouging and business collaboration

April 18, 2020

Burtley G. Francis and David Slipp During this unprecedented period of social isolation and economic uncertainty brought about by the COVID-19 pandemic, businesses are rapidly re-structuring their operations and adjusting their practices in order to…

Read More

Think: Roadmap to recovery

April 17, 2020

Rebecca Saturley COVID-19 hit us all like a proverbial freight train. In a short period of time we all went from business as usual to the new normal. From social distancing to mass lay-offs to…

Read More

Government passes COVID-19 Emergency Response Act, No. 2

April 13, 2020

(Updated) Peter McLellan, QC and Katharine Mack In a display of bi-partisanship, on Saturday, April 11 Parliament unanimously passed the COVID-19 Emergency Response Act, No. 2 and it received Royal Assent. In addition to other…

Read More

Nothing “palpable” in Pentastar dispute: trademark case confirms rules for statutory appeals

April 13, 2020

Daniela Bassan, QC The Federal Court recently upheld the decision of the Registrar of Trademarks in a dispute over the registration and use of the PENTASTAR word mark in Canada, in Pentastar Transport Ltd. v.…

Read More

Search Archive


Scroll To Top