Client Update: “Lien”-ing Towards Efficiency: Upcoming Amendments to the Builders’ Lien Act

By Brian Tabor, QC and Colin Piercey

Bill 81 and Bill 15, receiving Royal Assent in 2013 and 2014 respectively, are due to take effect this month. On June 30, 2017, amendments to the Builders’ Lien Act (“the Act”) will introduce new regulations following recommendations from the 2013 Builders’ Lien Act Report by the Nova Scotia Law Reform Commission.

Why the Change?

The goal of these amendments is two-fold: to improve the flow of payments between certain stages of a construction project and to ensure that notice of important milestones, as defined by the Act, is given to parties involved.

To achieve these goals, the following amendments will take effect:

  • A progressive release of holdbacks to subcontractors through certification
  • A change in “finishing holdbacks”
  • The creation of a written notice requirement of substantial performance and subcontract completion

These amendments respond to a number of concerns related to the management of construction projects, specifically related to holdbacks and notice of contract performance timelines. As stated in a backgrounder on the upcoming amendments to the Act, the holdback system currently operates through a “construction pyramid,” whereby the owner retains a holdback from the contractor, and in turn, the contractor retains a holdback from the subcontractor. For example, if a contractor fails to pay their subcontractors, these individuals have the ability to place a “lien” on the owner’s property for the amount owed. If the construction project finishes and no liens are registered, the holdback is released. In other words, a holdback is used to protect owners by limiting liability and subcontractors in the event that the contractor defaults on the contract. These protections will not change.

Progressive Release of Holdbacks through Certification

Under the current Builders’ Lien Act, ­­the holdback retained by the owner may only be partially released (absent any liens being held) upon substantial completion of the contract and fully released upon final completion of the contract.  However, earlier subcontractors are often disadvantaged by the delay in receiving the holdback payment, with no interest payable on the holdback amount in the interim.

The amendments due to take effect will allow owners to release a subcontractor’s holdback earlier by having the completion of the subcontract certified under Subsection 13A of the Act by an architect or an engineer, or in their absence, by a court. In other words, owners and purchasers of a particular construction project will be able to rely on verification from an independent and qualified third party to release the holdback as opposed to waiting until substantial completion of the entire project occurs. The earlier subcontractor can be paid sooner while the owner still retains the protection afforded by the Act.

Once the subcontract is certified as complete, the owner must pay out a proportion of the holdback amount within 60 days. If the subcontractor’s holdback is not paid out within 65 days of certified completion, the owner will be liable to the subcontractor for interest on the holdback amount at a rate of prime plus 2 percent.

A Change in Finishing Holdbacks

Another change to the Act is the way that finishing holdbacks will be calculated moving forward. The current Act requires the owner to retain a holdback of 2.5 per cent of the entire contract price to cover any potential liens against the property registered after the substantial performance deadline. In practice, this amount is often disproportionate to the actual cost of the work remaining.

The amendments will change the calculation percentage of the finishing holdback to 10 per cent of the cost of the remaining work (such as the cost of remaining supplies and materials) rather than using 2.5 per cent of the entire contract price.

Written Notice Requirement of Substantial Performance or Completion

The amendments will also introduce a new set of regulations, NS Reg 72/2017 to improve the notice to be given to parties involved in the contract upon substantial performance or upon final completion. In practice, parties involved in a construction contract may not be informed of these particular milestones. Notice is important as it often acts as a trigger for the release of holdbacks if no lien against the property is filed.

The new regulations will impose a duty upon owners to make written notice available to parties working on a particular construction project, whether it be contractors, subcontractors, suppliers, or employees. The application of the regulations will not apply to an owner, their spouse, or common law partner for constructing a structure or for improving a building or land for single-family residential purposes, up to $75,000.

When and how does an owner give notice?

  • Post notice of substantial completion or subcontract completion of the construction project (depending on the milestone) within 10 days of the milestone date
  • Post notice on the publicly available portion of the Construction Association of Nova Scotia (CANS) website at www.substantialperformance.com (no fee for publishing, viewing, or searching for notices)
  • If there is a job site office, post notice in a prominent location

What does an owner include for notice of substantial completion?

  • Name and address of the owner
  • Name and address of the contractor
  • Description of the work or services performed
  • Description of the land upon which the work or services were performed
  • Date the contract was substantially performed

What does an owner include for notice of subcontract completion?

  • Name and address of the owner
  • Name and address of the contractor
  • Name and address of the subcontractor
  • If a subcontract is certified as complete under Subsection 13A of the Act, the name and address of the architect, engineer, or other person to whom the certificate payments are to be made
  • Description of the work or services performed or the materials placed or furnished
  • Description of the land upon which the work or services were performed or the materials were placed or furnished
  • Date the contract was certified as complete

The foregoing is intended for general information only. If you have any questions about how these amendments may affect your business, please contact a member of our Construction Law practice group.

References:

SHARE

Archive

Search Archive


 
 

Client Update: Perrin v Blake reaffirms the law on contributory negligence and recovery of damages

April 14, 2016

In a case where there is a contributorily negligent plaintiff and two or more negligent defendants, can the plaintiff recover 100% of her damages from any of the defendants? The answer in Nova Scotia is…

Read More

Client Update: Interest arbitration changes for New Brunswick postponed for further study

April 11, 2016

On Friday, the Province of New Brunswick announced that it would not proceed at this time with the recently proposed changes to binding interest arbitration. The Province announced that a joint labour management committee will be struck to examine…

Read More

Client Update: Universal interest arbitration proposed for New Brunswick

April 5, 2016

On March 29, 2016, the Province of New Brunswick tabled proposed changes to the Industrial Relations Act and the Public Services Labour Relations Act. If passed, these changes would dramatically alter well-established principles of private sector collective bargaining.…

Read More

Good Faith Fisheries: New case on Crown consultation & regulation of Aboriginal fisheries

March 22, 2016

By Jennifer Taylor Why is this case a big deal? It started with two salmon. Now, after several years of litigation, the Nova Scotia Provincial Court in R v Martin, 2016 NSPC 14 has stayed proceedings against…

Read More

Atlantic Employers’ Counsel – Winter 2016

March 10, 2016

THE EDITORS’ CORNER Michelle Black and Sean Kelly One day, the line between mental and physical disabilities may not be so pronounced, but, for now, distinctions are still drawn between Employee A with, for example, diabetes and…

Read More

Hiring the “Right” Employee

February 24, 2016

By Lisa Gallivan Employees can be your biggest asset, if you hire the right people. This can often be one of the biggest decisions that you make as a business owner or employer. The “right” employee…

Read More

Bye, Bye Canadian P.I.?: What Apple’s fight against the FBI means for the protection of Personal Information in Canada

February 23, 2016

By Burtley Francis and Kathleen Leighton Order Up: Apple, P.I. Recently, the public safety versus personal privacy debate has been brought to main headlines. Apple is facing a court order (available here) requiring the company to assist the FBI in the investigation of…

Read More

Client Update: Outlook for the 2016 Proxy Season

February 12, 2016

In preparing for the 2016 proxy season, you should be aware of some regulatory changes and institutional investor guidance that may impact disclosure to and interactions with your shareholders. This update highlights what is new…

Read More

Left Sharks and Copy Cats: The Super Bowl’s Impact on Protecting a Brand

February 5, 2016

By Burtley Francis and Michael MacIsaac You remember Left Shark… The Super Bowl is a lot of things to a lot of people and is arguably the most anticipated event of the year that is not a holiday…

Read More

The Labour Relations of First Nations’ Fisheries: Who gets to decide?

February 2, 2016

By Jennifer Taylor Summary The Canada Industrial Relations Board recently held that it had no jurisdiction as a federal board to certify a bargaining unit comprised of fisheries employees of the Waycobah First Nation. The decision…

Read More

Search Archive


Scroll To Top