Skip to content

New Brunswick introduces prompt payment and adjudication legislation

By Conor O’Neil and Maria Cummings

On May 9, 2023, two bills were introduced in the New Brunswick Legislature that could have material affects on the construction industry. Bills 41 and 42, of the current session, if passed, would amend the Construction Remedies Act, and introduce a new companion act which would establish mandatory prompt payment and adjudication for construction projects. As of the writing of this article, both bills are working through the legislature and will not become law unless passed in this session.

Bill 41, an Act respecting holdback trust accounts

Bill 41, if passed, will amend the Construction Remedies Act to repeal the requirement for an owner to maintain a holdback trust account for each improvement with a joint trustee. The requirement to maintain holdback by an owner will remain but the practical effect will be to return to the practice under the historical Mechanics’ Lien Act whereby an owner is not required to deposit the holdback into a separate trust account.

Bill 42, Construction Prompt Payment and Adjudication Act

Bill 42, if passed, will introduce a completely new act, the Construction Prompt Payment and Adjudication Act (the “Act”). The application of the Act is defined almost identically to the Construction Remedies Act. In other words, it will apply to almost any construction contract, although there is potentially broad authority to exempt certain classes of improvements, persons or contracts in the regulations. Its effect will be to introduce a new regime including prompt payment and adjudication.

Prompt payment legislation is aimed at the perception of systemic slow or non-payment in the construction industry. The first Canadian prompt payment bill was introduced in Ontario in 2017. Since then prompt payment and adjudication legislation has been considered in a majority of provinces, and federally, many of which have introduced and passed their own bills, although it is not in force in every jurisdiction in which a bill has been introduced.

The prompt payment portion of the Act prescribes time periods in which payment must flow through the construction pyramid. After the delivery of a “proper invoice” by a contractor to an owner, the owner has 28 days in which it must pay the proper invoice. The owner may dispute the proper invoice by issuing a notice of non-payment within 14 days of receipt of the proper invoice. Even if a notice of non-payment is issued, the owner must pay the undisputed portion of the proper invoice within the same 28-day window.

The time period for payment cascades down the construction pyramid through direct contracting parties. For example, upon receipt of payment on the 28th day by the contractor, that contractor then has 7 days in which to provide payment to its subcontractor(s) (i.e. by day 35). Similarly, upon receipt of payment by a subcontractor it must pay its sub-subcontractors or suppliers within 7 days (i.e. by day 42).

Adjudication provides the teeth to enforce prompt payment. A common criticism of traditional dispute resolution processes, like litigation or arbitration, is that they are too slow and disputes choke off the cash flow necessary for projects to continue on to completion. Adjudication provides a new option that has been described as an interim-binding dispute resolution.

The Act provides that much of the actual process for adjudication will be set out in the regulations, or by the adjudicator nominating authority. However, in other jurisdictions the intent has been that where there is a dispute as to payment that dispute may be referred to a third-party adjudicator and a decision on the dispute may be rendered in as little as 39 to 60 days. The concept is that the decision of the adjudicator is only binding on the parties to a dispute until the project is substantially performed. In theory, this increases cash flow and provides an interim mechanism for the parties to complete the project. Parties that are unhappy with the result of an adjudication are free to litigate or arbitrate after the fact.

Other provinces have taken varied approaches to the appointment of an adjudicator nominating authority and the training and certification of adjudicators. The regime as a whole has been met with mixed reviews on its success. Prompt payment and adjudication is still in its infancy across Canada and it remains to be seen how this could be effectively implemented in New Brunswick.


This client update is provided for general information only and does not constitute legal advice. If you have any questions about the above, please contact the authors.

Click here to subscribe to Stewart McKelvey Thought Leadership.

SHARE

Archive

Search Archive


 
 

Client Update: Jury Duty – Time to Think Twice

June 6, 2013

The integrity of the jury system has become a pressing topic for our courts of late, with articles about jury duty frequently appearing front and centre in the press. The recent message from the Nova…

Read More

Doing Business in Atlantic Canada (Summer 2013)(Canadian Lawyer magazine supplement)

June 2, 2013

IN THIS ISSUE: Cloud computing: House to navigate risky skies by Daniela Bassan and Michelle Chai Growing a startup by Clarence Bennett, Twila Reid and Nicholas Russon Knowing the lay of the land – Aboriginal rights and land claims in Labrador by Colm St. Roch Seviour and Steve Scruton Download…

Read More

Client Update: The Personal Health Information Act (PHIA) is coming…..

May 27, 2013

DOES IT APPLY TO YOU? On June 1, 2013, the Personal Health Information Act (PHIA) comes into force in Nova Scotia.  If you are involved in health care in Nova Scotia, you need to know whether PHIA…

Read More

Atlantic Employers’ Counsel – Spring 2013

May 22, 2013

EDITOR’S COMMENT This edition of Atlantic Employers’ Counsel focuses on key areas of employment standards in Atlantic Canada. Employment standards legislation outlines the rights and obligations of employees and requirements that apply to employers in…

Read More

Client Update: Nova Scotia New tort of cyberbullying

May 17, 2013

NEW TORT OF CYBERBULLYING On May 10, 2013 the Nova Scotia legislature passed the Cyber-safety Act (Bill 61). When this bill comes into force, it will give rise to a new tort of cyberbullying that…

Read More

Client Update: Lender Code of Conduct Prepayment of Consumer Mortgages

May 2, 2013

GOVERNMENT ACTION In the Economic Action Plan 2010, the Harper Government committed to bring greater clarity to how mortgage prepayment penalties were calculated. As part of the commitment, on February 26, 2013 the government released…

Read More

Client Update: Corporate Services – Keeping you up to date

March 7, 2013

STEWART MCKELVEY WELCOMES BACK WANDA DOIRON AS MANAGER, CORPORATE SERVICES – NOVA SCOTIA You might remember Wanda from her time in our Corporate Services group from 2002 to 2008. Since then, she has worked in-house…

Read More

Atlantic Employers’ Counsel – Winter 2013

March 6, 2013

REASONABLE PEOPLE DOING QUESTIONABLE THINGS: CONFLICTS OF INTEREST AND JUST CAUSE Can a unionized employee moonlight in his off hours to earn some extra money by doing the same work he does for his daytime…

Read More

SVILA E-Discovery

March 5, 2013

Stewart McKelvey’s Vision Improving Legal Analysis (SVILA*) is an e-discovery project and litigation management tool. For more information on our e-discovery services, download the SVILA e-discovery document.

Read More

Doing Business in Atlantic Canada (Spring 2013)(Canadian Lawyer magazine supplement)

March 5, 2013

IN THIS ISSUE: A New Brunswick business lawyer’s perspective by Peter Klohn Why Canada’s immigration rules matter to your business by Andrea Baldwin Financing Energy Projects during the Project Lifecycle by Lydia Bugden, Colm St. Roch Seviour and Tauna Staniland Download…

Read More

Search Archive


Scroll To Top