The end of the Mechanics’ Lien Act

Kenneth McCullogh, QC and Conor O’Neil, P.Eng.

On December 18, 2020, the Legislative Assembly of New Brunswick passed the Construction Remedies Act. The new legislation will not take effect until a date to be named at which time it will replace the existing Mechanics’ Lien Act (“Act”). The new legislation is lengthy and technical in nature compared to its predecessor. As anticipated the new Act does not include provisions for prompt payment or adjudication which have been passed in other provinces, although the door has been left open for such provisions at a later date.

Modernization of the Act

Many of the changes will be familiar to those who work in jurisdictions outside New Brunswick. As in almost all other provinces, the statutory holdback amount which is required to be retained by an owner will be reduced from 15% of the contract price to 10%.

Similarly, the time within which a lien holder has to register its claim for lien will be harmonized to a single 60 day period. In most instances that 60 day period will run from the earliest of the date of certification of substantial performance, completion, termination or abandonment of the contract. Importantly for subcontractors, the time period will also be triggered by the date upon which the subcontractor last supplied services or materials to the improvement. This provides clarification for certain subcontractors, for example earthworks, who supply their services early in a project and do not stay on for the entire life cycle.

A subtle, but significant, new change will be that parties can no longer contract out of their lien rights. The new legislation specifically provides that every contract or subcontract is deemed to be amended to conform to the new Act.

Substantial performance and completion of projects

The new Act offers some clearer direction for determination of when a contract is substantially performed and completed. As to substantial performance, the test that the improvement be ready for use or the purpose intended is codified; however, a second criteria will be in place which requires that the improvement be capable of completion or that the remaining defects be less than a certain amount, for which the new Act provides a formula. Similarly, completion requires that the cost of completing the improvement be less than 1% of the contract price.

The Construction Remedies Act will more strictly limit who can perform the role of payment certifier to an architect, engineer or a third party designated in the contract. A contractor will have the ability to directly request that the payment certifier determine if the contract is substantially performed. The new Act also prescribes times within which the payment certifier will deliver its certificate. Finally, the contractor will be required to post the certificate of substantial performance at the site of the improvement. The new Act leaves open the possibility that other forms of notice may be prescribed by regulation. The government has previously signaled that it would be preferable if an industry association take on the role of publishing certificates of substantial performance online, as is done in trade publications in some other jurisdictions. This would have the effect of providing more timely and consistent notice to subcontractors and suppliers that the clock is ticking for the release of holdback and expiration of lien rights on projects.

Where a contract is substantially performed and some services or materials remain to be supplied, the owner will be required to maintain a finishing holdback. The finishing holdback applies to the amount which remains to be completed after substantial performance, representing 10% of that amount. The finishing holdback may be released 60 days after the completion, abandonment or termination of the contract.

Release of holdback after the lien period expires will become mandatory, rather than permissive. Owners and payment certifiers that have in the past converted the statutory holdback to a deficiency holdback after the period for registration of a claim for lien has expired will no longer be able to do so. Owners will want to carefully keep track of such amounts to avoid the issue of not retaining enough funds to complete a project. For longer projects the Construction Remedies Act also provides that holdback may be released on an annual or phased basis.

Trust accounts and breach of trust

The trust provisions of the new lien legislation will be significantly altered. The obligations of owners, in particular, will greatly expand. As was always the case, the contractor and subcontractor trusts remain.

Funds in the hands of an owner will become trust funds when the funds become payable to the contractor. Owners will also be required to establish a holdback trust account for such funds with their financial institution in an account separate and apart from other funds for the project. This account is to be administered, in most cases, by the owner and the contractor. Any payments made out of the holdback trust account require the signature of each of the trustees and trustees are required to maintain records to ensure that the funds are traceable.

Finally, a breach of the trust provisions remains an offence under the Provincial Offences Procedures Act; however, directors, officers and any person who has effective control of the corporation that assents to, or acquiesces in conduct that the person knows, or reasonably ought to know, would result in a breach of trust may be liable for such a breach. This means trustees may be personally sued in the Court of Queen’s Bench for breach of trust by beneficiaries of the trust.

What’s next

Government is now drafting regulations under the Construction Remedies Act and it is not anticipated that the Act will come into effect until the regulations are complete.

For the time being the Mechanics’ Lien Act continues to apply to all construction projects in New Brunswick. When the transition happens, the new legislation provides that contracts entered into after the Construction Remedies Act comes into force will be governed by the new legislation. There will be a period of grandfathered contracts as the Mechanics’ Lien Act will continue to apply to any contracts which are entered into before the date upon which the Construction Remedies Act comes into force.


This update is intended for general information only. If you have questions about how the information above may affect you, please contact any member of our construction group.

SHARE

Archive

Search Archive


 
 

$82 billion federal government aid package – high points for employers

March 18, 2020

The Federal Government just announced various COVID-19-related measures in its Canada’s Covid-19 Economic Response Plan: Support for Canadians and Businesses.  The full statement can be found here. The following may be of particular interest to…

Read More

Nova Scotia announces mandatory quarantine for public sector staff and students returning from outside Canada

March 13, 2020

Brian Johnston, QC and Jennifer Thompson In an effort to mitigate the spread of COVID-19 in Nova Scotia, Premier Stephen McNeil and Chief Medical Officer, Dr. Robert Strang have announced that all public sector employees…

Read More

Government of Canada announces changes to Employment Insurance and Work-Share Program as part of $1 billion COVID-19 fund

March 12, 2020

Jennifer Thompson As employees and employers grapple with the practical implications of a potential COVID-19 outbreak, the Government of Canada has stepped up to the plate with an announcement of a $1 billion fund to…

Read More

COVID-19: Keep calm and consider the issues!

March 6, 2020

Rick Dunlop, Jennifer Thompson, Alycia Novacefski, Kyle Hartlen, Scott Campbell and Rebecca Saturley The impact of COVID-19, commonly referred to as coronavirus, will vary by organization. Each organization, however, should consider various legal issues associated…

Read More

Nova Scotia releases new pension funding framework, effective April 1, 2020

February 28, 2020

Level Chan and Dante Manna On February 26, 2020, the Nova Scotia Government released its regulations establishing a new defined benefit pension funding framework for the province. The amendments to the Pension Benefits Regulations (“PBR”)…

Read More

Richards Estate sets the limits on actions against LTD insurers

February 27, 2020

Michelle Chai & Jennifer Taylor   UPDATE   Richards Estate v Industrial Alliance Insurance and Financial Services Inc, 2020 NSCA 14   The Nova Scotia Court of Appeal has recently overturned the decision summarized below,…

Read More

Can my child obtain a work permit?

February 27, 2020

Kathleen Leighton Family reunification is a top priority for Canada when it comes to immigration, and we recognize that in order to continue to attract skilled workers to our country, we must ensure there are…

Read More

Bringing top talent to Canada’s educational institutions

February 19, 2020

Kathleen Leighton and Brittany Trafford Canada’s higher education institutions power innovation and contribute to economic growth through research and development efforts, collaborations with government and industry and the provision of world-class educational programming to develop…

Read More

Express yourself … but maybe not on your license plate: The NSSC decision in Grabher

February 6, 2020

Jennifer Taylor   The case of Lorne Grabher and his personalized “GRABHER” license plate has grabbed many headlines. Mr. Grabher (“Applicant”) launched a constitutional challenge after Nova Scotia’s Registrar of Motor Vehicles cancelled his personalized…

Read More

Ensuring your earn-out turns out: A review of the law of earn-out clauses in Canada

February 5, 2020

David Randell and David Slipp With a number of economic indicators showing headwinds ahead, purchasers and vendors are likely to have a more challenging time agreeing on a target company’s valuation. In these cases, parties…

Read More

Search Archive


Scroll To Top