The end of the Mechanics’ Lien Act

Kenneth McCullogh, QC and Conor O’Neil, P.Eng.

On December 18, 2020, the Legislative Assembly of New Brunswick passed the Construction Remedies Act. The new legislation will not take effect until a date to be named at which time it will replace the existing Mechanics’ Lien Act (“Act”). The new legislation is lengthy and technical in nature compared to its predecessor. As anticipated the new Act does not include provisions for prompt payment or adjudication which have been passed in other provinces, although the door has been left open for such provisions at a later date.

Modernization of the Act

Many of the changes will be familiar to those who work in jurisdictions outside New Brunswick. As in almost all other provinces, the statutory holdback amount which is required to be retained by an owner will be reduced from 15% of the contract price to 10%.

Similarly, the time within which a lien holder has to register its claim for lien will be harmonized to a single 60 day period. In most instances that 60 day period will run from the earliest of the date of certification of substantial performance, completion, termination or abandonment of the contract. Importantly for subcontractors, the time period will also be triggered by the date upon which the subcontractor last supplied services or materials to the improvement. This provides clarification for certain subcontractors, for example earthworks, who supply their services early in a project and do not stay on for the entire life cycle.

A subtle, but significant, new change will be that parties can no longer contract out of their lien rights. The new legislation specifically provides that every contract or subcontract is deemed to be amended to conform to the new Act.

Substantial performance and completion of projects

The new Act offers some clearer direction for determination of when a contract is substantially performed and completed. As to substantial performance, the test that the improvement be ready for use or the purpose intended is codified; however, a second criteria will be in place which requires that the improvement be capable of completion or that the remaining defects be less than a certain amount, for which the new Act provides a formula. Similarly, completion requires that the cost of completing the improvement be less than 1% of the contract price.

The Construction Remedies Act will more strictly limit who can perform the role of payment certifier to an architect, engineer or a third party designated in the contract. A contractor will have the ability to directly request that the payment certifier determine if the contract is substantially performed. The new Act also prescribes times within which the payment certifier will deliver its certificate. Finally, the contractor will be required to post the certificate of substantial performance at the site of the improvement. The new Act leaves open the possibility that other forms of notice may be prescribed by regulation. The government has previously signaled that it would be preferable if an industry association take on the role of publishing certificates of substantial performance online, as is done in trade publications in some other jurisdictions. This would have the effect of providing more timely and consistent notice to subcontractors and suppliers that the clock is ticking for the release of holdback and expiration of lien rights on projects.

Where a contract is substantially performed and some services or materials remain to be supplied, the owner will be required to maintain a finishing holdback. The finishing holdback applies to the amount which remains to be completed after substantial performance, representing 10% of that amount. The finishing holdback may be released 60 days after the completion, abandonment or termination of the contract.

Release of holdback after the lien period expires will become mandatory, rather than permissive. Owners and payment certifiers that have in the past converted the statutory holdback to a deficiency holdback after the period for registration of a claim for lien has expired will no longer be able to do so. Owners will want to carefully keep track of such amounts to avoid the issue of not retaining enough funds to complete a project. For longer projects the Construction Remedies Act also provides that holdback may be released on an annual or phased basis.

Trust accounts and breach of trust

The trust provisions of the new lien legislation will be significantly altered. The obligations of owners, in particular, will greatly expand. As was always the case, the contractor and subcontractor trusts remain.

Funds in the hands of an owner will become trust funds when the funds become payable to the contractor. Owners will also be required to establish a holdback trust account for such funds with their financial institution in an account separate and apart from other funds for the project. This account is to be administered, in most cases, by the owner and the contractor. Any payments made out of the holdback trust account require the signature of each of the trustees and trustees are required to maintain records to ensure that the funds are traceable.

Finally, a breach of the trust provisions remains an offence under the Provincial Offences Procedures Act; however, directors, officers and any person who has effective control of the corporation that assents to, or acquiesces in conduct that the person knows, or reasonably ought to know, would result in a breach of trust may be liable for such a breach. This means trustees may be personally sued in the Court of Queen’s Bench for breach of trust by beneficiaries of the trust.

What’s next

Government is now drafting regulations under the Construction Remedies Act and it is not anticipated that the Act will come into effect until the regulations are complete.

For the time being the Mechanics’ Lien Act continues to apply to all construction projects in New Brunswick. When the transition happens, the new legislation provides that contracts entered into after the Construction Remedies Act comes into force will be governed by the new legislation. There will be a period of grandfathered contracts as the Mechanics’ Lien Act will continue to apply to any contracts which are entered into before the date upon which the Construction Remedies Act comes into force.


This update is intended for general information only. If you have questions about how the information above may affect you, please contact any member of our construction group.

SHARE

Archive

Search Archive


 
 

Client Update: Reaching New Limits – Recent Amendments to the PEI Lands Protection Act

January 6, 2015

During the Fall 2014 legislative sitting, the Province of Prince Edward Island passed legislation that results in significant changes to the Lands Protection Act. The amendments have just been proclaimed and were effective January 1, 2015.…

Read More

Atlantic Employers’ Counsel – Fall 2014

December 17, 2014

The Editor’s Corner Clarence Bennett This issue focuses on the family and the interaction between employment and family obligations. As 2014 comes to a close, I would like to extend Seasons Greetings to all of…

Read More

Client Update: Recent Developments: Disability Insurance Policies

December 17, 2014

RECENT DEVELOPMENTS: DISABILITY INSURANCE POLICIES & LIMITATION PERIODS IN NOVA SCOTIA Two recent Nova Scotia decisions have clarified the issue of limitation periods in disability insurance policies and “rolling” limitation periods.   THORNTON V. RBC…

Read More

Client Update: Changes to Related Party Election (Section 156 – Excise Tax Act)

December 16, 2014

Section 156 of the Excise Tax Act (the “ETA“) provides an election that relieves certain related parties from having to collect Harmonized Sales Tax (“HST“) on the goods and services sold between them. The election deems qualifying…

Read More

Doing Business in Atlantic Canada (Fall 2014) (Canadian Lawyer Magazine Supplement)

November 20, 2014

IN THIS ISSUE: More Than Wind – Emergence of Tidal Energy in Atlantic Canada by Sadira Jan Aquaculture and Salmon Farming in Atlantic Canada by Greg Harding The Expanding Atlantic Canada Offshore Industry: Growing Offshore without Going Offside by Stephen Penney and Rebecca…

Read More

Client Update: Truth or Consequences – The New Duty of Honest Performance in Commercial Contracts

November 17, 2014

The Supreme Court of Canada’s unanimous decision in the breach of contract case Bhasin v Hrynew, 2014 SCC 71 was released on November 13, 2014. The case is important in the law of contracts because…

Read More

Client Update: Recent Changes to the Temporary Foreign Worker Program

August 28, 2014

On June 20, 2014, the Government of Canada announced a series of reforms to overhaul the Temporary Foreign Worker Program (“TFWP”). These reforms, many of which are effective immediately, function to: Re-organize the TFWP  The…

Read More

Atlantic Employers’ Counsel – Summer 2014

August 1, 2014

The Editor’s Corner Clarence Bennett Summer is halfway over, but we know you will want to take this edition along with you while you enjoy more summer weather and time out of the office. Employers…

Read More

Client Update – Tsilhqot’in Nation – An East Coast Perspective

July 9, 2014

On June 26, 2014, the Supreme Court of Canada released one of the most significant aboriginal law decisions since Marshall – Tsilhqot’in Nation v. British Columbia, 2014 SCC 44 (also known as the William decision).  This decision could have…

Read More

Client Update: Nova Scotia Supreme Court awards $500,000 in Punitive Damages in LTD case

July 9, 2014

In Industrial Alliance Insurance and Financial Services Inc. v. Brine, 2014 NSSC 219, National Life (and later its successor Industrial Alliance) alleged Brine had received undisclosed CPP and Superannuation disability benefits resulting in a substantial overpayment of…

Read More

Search Archive


Scroll To Top