The Winds of Change (Part 6): Place your bids – Crown lands soon to be available for wind energy projects
By John Samms, Stuart Wallace and Dave Randell
On December 14, 2022, the Newfoundland and Labrador Department of Industry, Energy and Technology announced the launch of a Crown land call for bids for wind energy projects. The document Guidelines: Crown Land Calls for Bids for Wind Energy Projects outlines the information required for bidders, including evaluation criteria. While the document should be reviewed for complete details of the process, this article is intended to provide a brief overview of the process.
Call for Bids
Bids can now be submitted for wind developments on Crown lands, and will be accepted from December 14, 2022 until midnight on March 3, 2023. Bids must be submitted via email to the Department of Industry, Energy and Technology. Available Crown lands for these projects can be viewed here.
Information for Evaluation
Bidders will be expected to provide, among other things, the following information for evaluation:
- Project summary;
- Associated Hydrogen/Ammonia production;
- Water requirements;
- Project risk mitigation;
- Electricity considerations and grid impacts;
- Community and Indigenous engagement;
- Project schedule; and,
- Financing.
Legislation
It is imperative that bidders review the province’s legislative and regulatory frameworks, including, but not limited to, those pertaining to the development and provision of electricity in the province, such as, the Public Utilities Act and the Electrical Power Control Act, 1994.
Evaluation of Bids
There will be a two-phased evaluation of bids.
Phase 1 Review – Minimum Criteria
First Stage Review will evaluate whether submissions meet the minimum criteria expected of a bidder to be able to deliver a Wind Energy Project. Emphasis will be placed on the bidder’s experience, the project, and their financial capacity to plan, construct, and operate the proposed project.
Phase 2 Review
Those successful in Phase 1 will automatically proceed to a Phase 2 review. This will begin in April 2023. This will be a more robust evaluation focused on the entirety on the information provided. The second stage review involves a weighted evaluation system, whereby electricity considerations and grid impacts are evaluated as heavily as bidder details, project details, benefits, and financing. The weighting is listed as follows:
- Bidder: 15%
- Project Risk Mitigation: 5%
- Electricity Considerations and Grid: 15%
- Community and Indigenous Engagement: 10%
- Benefits: 15%
- Project Schedule: 10%
- Financing: 10%
Successful Bidders
Successful bidders will not be awarded Crown land at the outset. Instead, the province utilized mechanisms under the Lands Act to proactively reserve certain lands to later grant successful proponents the exclusive right to formally apply for an interest in the property. The provincial government will then provide successful proponents a wind application recommendation letter from the Department. This will serve as the instrument that guarantees a proponent an exclusive window to secure relevant Crown land, subject to the various legislation including the Public Utilities Act and the Electrical Power Control Act, 1994.
This update is intended for general information only. If you have any questions on the above we would invite you to contact the authors or any other member of our Energy Group.
Click here to subscribe to Stewart McKelvey Thought Leadership
Archive
By Jennifer Taylor Introduction There is now a Nova Scotia decision on the interplay between the provincial Builders’ Lien Act and the federal Bankruptcy and Insolvency Act (“BIA”) in the interesting context of trusts. In Re Kel-Greg Homes Inc, Justice Rosinski…
Read MoreThe New Brunswick government is seeking feedback from stakeholders on proposed changes to the Employment Standards Act (“Act”). The proposed changes relate to: – the statutory minimum wage; – employment protections for young workers; and – coverage…
Read MoreOCTOBER 19, 2015 – FEDERAL ELECTION A Federal election has been called for Monday, October 19, 2015. Polls are open in Atlantic Canada from 8:30 a.m. to 8:30 p.m. Advance polls are open from…
Read MoreAs of August 1, 2015, section 4 of the Nova Scotia Automobile Tort Recovery Limitations Regulations was repealed. This section previously set the discount rate for future losses in automobile tort claims at 3.5%. The repeal…
Read MoreOn September 9, 2015, the Nova Scotia Department of Finance and Treasury Board opened a consultation on draft Regulations for Pooled Registered Pension Plans (PRPPs). The draft Regulations and an FAQ are posted online. PRPPs are…
Read MoreBy Jennifer Taylor – Research Lawyer September used to mean one thing: back to school. This year, Nova Scotia lawyers get a fresh learning opportunity of a different sort. It comes in the form of the new Limitation…
Read MoreTHE EDITORS’ CORNER Michelle Black and Sean Kelly Aaah, summer – that long anticipated stretch of lazy, lingering days, free of responsibility and rife with possibility. It’s a time to hunt for insects, master handstands, practice swimming…
Read MoreThe New Public Contracting World As part of an ongoing initiative aimed at ensuring Canada only does business with ethical suppliers, Public Works and Government Services Canada (“PWGSC”) has introduced changes to its Integrity Regime…
Read MoreIn an important case for insurance practice in Nova Scotia, the Court of Appeal has confirmed that the value of future CPP disability benefits is deductible under the SEF 44 family protection endorsement. Justice Scanlan wrote the…
Read MoreIn order to streamline the continuous disclosure obligations of venture issuers, the Canadian Securities Administrators (“CSA”) are implementing amendments to the national instruments and companion policies listed below, that will come into force across Canada…
Read More